|
Maintenance Management Case Study
With maintenance crews working too much overtime, management frustrated
about equipment performance, an underutilized CMMS, pressure to improve
performance, and nagging questions about maintenance effectiveness that
could not be answered, this western manufacturer knew they needed to do
something significantly different. Additional resources or a new strategy
were not the answers, improved execution was.
Can a maintenance department led by 20, 30 and 40-year veterans change
the way they operate to improve performance? Absolutely. Was it easy?
Certainly not. Was it beneficial? Read on...
Within one of North America's 500 largest manufacturing companies, this
maintenance department's situation was similar to many others; filled with
hard working tradesmen with decades of technical experience, but with few
processes and tools in place to manage performance within the department.
It was popular opinion that there were things that could be done to
improve overall performance. A statement reinforced by the site's General
Manager, "we were not maximizing the productivity or efficiency of the
equipment we already had in place, we wanted to make sure we're getting the
most out of what we had before we went asking for capital to make
improvements. There was room there to do better with what we had." How
much more? During an initial analysis, millions of dollars in opportunity
were identified across the operation based on increased throughput and
finished-goods quality, not on short-term cost cutting measures.
Supported by comments from the management team that included "we need
a system to ensure maintenance work doesn't slip through the cracks" and
"it doesn't matter how many maintenance staff we have, it never seems to
be enough", it was clear that maintenance needed to be part of the solution.
Two sets of maintenance issues needed to be addressed in order to help
capture this multi-million dollar opportunity. First, the process in
place to plan and execute work would need to be refined, and secondly, a
process to manage the maintenance department's performance would need
to be implemented.
When asked about dealing with these issues on their own the GM
responded, "we're short handed with the current maintenance group; we just
didn't have the resources required to design and implement a system
that would get us to where we wanted to be in a very short window."
So was it an easy decision to bring in Perforex as part of the
solution? The GM continues "even if we only capture 50% of the
opportunity identified, we'd be crazy not to go ahead with a project.
On the other hand you are saying there is all this opportunity; you
have to be comfortable enough with yourself to say 'hey maybe we're
good at what we do but we can be an awful lot better', so your ego
needs to be in check."
So with that, management decided to engage Perforex for a
performance improvement initiative that included in-depth work
within the maintenance department.
Together with hourly and salaried staff, Perforex first
worked to design and implement a site-specific system that would
enable the maintenance department to identify, plan, schedule,
assign, execute, sign off and close maintenance work. This meant
designing a series of user-friendly tools that would not be
intimidating to a seasoned maintenance staff. Revising work request
forms, confirming preventative maintenance lists, designing planning tools
and making the weekly planning meeting more robust were all part of the
solution. Conceptually, all of these tools were straightforward, the
challenge was in working with plant staff to put them to use in a
disciplined and effective way.
Implementing a system to manage the maintenance department for
performance was the next step. Going beyond typical maintenance measures
such as up-time percentages and overtime costs, a complete set of
performance indicators was developed that focused on the effectiveness
of the maintenance function from a planning and execution perspective.
Focusing on the specifics that the maintenance group actually controls
allowed them to look at their own performance more critically and
take steps to improve it.
This all adds up to significant process changes and even bigger
cultural changes. As management says, "we are used to measuring
production performance every shift and every hour, and while specific
measures are needed to assess maintenance performance, we knew that
implementing them would represent a huge change."
The GM was asked his opinion regarding the process that his organization went
through, "it isn't Perforex coming in and saying this is what the answer is. It is
Perforex coming in and leading our own people as a group, from the shop floor
to management, through the design of how to better manage. That's what I
like about it, it gets our people involved, I needed that so our people could
learn the process because one day Perforex is going to go away and when they
are gone I don't just want to go back to where we were."
So what? Are things any better now? According to the GM, yes, "sure the
financial benefits are important to me, but we knew we needed to realign
maintenance and the Perforex approach gave my maintenance superintendent a
good set of tools to do this." He continues, "we were prioritizing each day
by who screamed the loudest, and now we are planning our work based on what is
best for the entire operation."
As the Maintenance Superintendent explains, things are different now,
"historically, we put a lot of value on the maintenance crew's ability to save
the day when we had unplanned downtime, now the crew knows that we don't pat
people on the back for getting us out of a ditch, we pat people on the back for
keeping us out of the ditch."
Download the PDF Version
|